Spring is coming! I need to be done with the bathroom! There are a lot of things to do outside now that spring is here. Instead on Friday a little mastic was mixed up and the three tiles were set. We then went out to the old chicken coop and brought in all of the blue pine tongue and groove siding. We measured it and I did the math, we should have an extra 6 sq feet. The air compressor and nailers were drug out and we determined that we don’t have any 16 gage finish nails short enough. Some will have to be purchased. The 18 g nailer will only take 1.25” nails and I want at least 1.5”. Those are now purchased and ready to go.

Since we now had to wait for the bathroom to dry out for a day before patching the grout we went outside and started to drag the gravel road in an attempt to work out the potholes. We spent a couple of hours dragging the driveway with the box blade and the arena groomer. It turned out pretty good and there are currently no pot holes in the driveway.


We have been having so many lambs that Mr Rainman and I ended up rearranging the barn. We made the momma/baby area bigger.
Saturday a batch of epoxy grout was mixed up. All I had to do was patch the bad areas and then clean every hour. I did this and two hours later found three little pin holes. A fresh batch of grout had to be mixed up so I could swipe a single time in a single spot. It was some serious overkill but totally necessary. We have one batch of grout left if needed.

I unpacked the inset vanity that goes over the toilet. I thought I was going to have to set it first before putting up the tongue and groove wall board. It was going to require a lot of specialize cuts. I traced out the cupboard pattern onto the plywood so I could start getting a feel for how I was going to cut this board. Annmarie came in, looked at it and said that I could just set the insert over the wall boards! This will make it so much easier. I plan on getting the wallboards installed next weekend. Mr Rainman will be gone and it is something I can do without any help.
Annmarie and I are so confident of the shower that we ordered the shower curtain rod and soap holders. I will be finishing the plumbing install next weekend also. I was informed that the rest of the bathroom can be a work in progress as long as the shower works.
Looking good!